Baseline trailer-mounted generator used for temporary and emergency power generation.

Due Diligence and Risk Assessment

Due diligence and risk assessment Overview

 

Because of the risks involved in financing energy projects, financial institutions and developers depend on qualified third-party assessment of project risks, from inception and operation to covering the life of the projects. Each financed project has its own attributes governing its technical, legal, and economic objectives. Danovo Energy Solutions experts, advisors, and analysts are fully immersed in the technical, legal, and economic risks of the energy industry. We are aware of possible ways to measure and mitigate (to the extent possible) identified risks. We are also aware of these diverse risks from the project developer side as well as from the potential investors and debt providers’ sides.

Due Diligence

Service Offerings

Independent Engineering Review and Assessment

 

  • Project site due diligence
  • Site visit and layout
  • Permits and environmental issues
  • Site control and access
  • Civil and geotechnical investigation
  • Project design due diligence
  • Project configuration and technology

Independent Engineering Review and Assessment

  • Electrical and balance of plant (BOP)
  • SCADA, metering, communication, and monitoring
  • Protection and regulatory compliance
  • Energy production due diligence
  • Energy forecast
  • Energy losses, degradation, and efficiency
  • Reliability and maintenance schedules
  • Equipment replacement and end of life (EOL)

Bankability Objectives

  • All risks are properly identified
  • Risks are indexed and/or costed/priced in a matrix
  • No unidentified risks remain
  • Investors have committed equity
  • Banks/financial institutions to fund debt
Due diligence circles for risk matrix and mitigation measures.
Due diligence circles for risk matrix and mitigation measures.
Bankability objectives and risk management for due diligence with circles and arrows.

Why Danovo Energy Solutions?

We understand the overall risks involved when a diverse group of energy stakeholders must take a project from the greenfield development stage into inception and beyond. Danovo Energy Solutions technical, financial, practical, and economic expertise to provide robust and reliable project bankability assessments is unparalleled. Our Transmission & Regulatory group has been fully engaged in energy project development and project financing on individual projects and project portfolios. This experience provides the group with a solid foundation for proper and defendable bankability reviews, assessments, and recommendations (based on inputs from a wide range of experiences). The group utilizes many tools for its in-house assessment including market pricing forecast software and its proprietary financial pro-forma model.

Contact us to learn more about Due Diligence